Sept. 21, 2018 Update

Here's what is happening on Project2018 for the Sept. 21, 2018 update:

Drainage Work

Concrete footers were laid on the new addition to the south side of the existing high school.

Extra support and drainage were added to the south drive to ensure a lasting product.

Underground plumbing was placed to help with waste disposal from new science classrooms.

View the Powerpoint
Sept. 21, 2018